ADMINISTRATIVE CONTROL HEADQUARTERS BUILDINGS COMPLEX

Construction of the New Headquarters buildings complex of the Administrative Control Authority, which includes Seven buildings, the Project land area 75,600 m2 and total Built up area =136,750.00 m2
Client

Engineering Authority of the Egyptian Armed Forces

Duration

2017 - 2023

Contract Value

221 Million USD

Type

ADMINISTRATIVE CONTROL HEADQUARTERS BUILDINGS COMPLEX

Construction of the New Headquarters buildings complex of the
Administrative Control Authority, which includes Seven buildings, the
Project land area 75,600 m2 and total Built up area =136,750.00 m2

 

PROJECT COMPONENT
1- The Main building
2- Administrative Control Building No. (1)
3- Administrative building
4- Conference hall building
5- Mosque
6- Service Buildings and Gates
7- Administrative Control Building No. (2)
8- Basement.
9- Electrical Substations room

SCOPE SUMMARY
• Topographical and Geotechnical Works
• Development of Detailed designs till IFC drawings to complete Scope of Works for:
– Architectural, Structural and Electro-Mechanical works
– Medical gas system for Hospital
– Air conditioning and ventilation Systems
– Elevator works
– General layout and landscape
• Core & Shell (Architectural and facades, Structural and Electro-Mechanical works, site development) of all Buildings and facilities.